Tuesday, November 27, 2012

Appointment of Senior Counsel in Victoria for 2012

The Chief Justice Marilyn Warren AC has announced the appointment of Senior Counsel in Victoria for 2012. The list is as follows:

Trevor Stanley Monti
Suzanne Bridget McNicol
Peter George Sest
Aileen Mary Ryan
Christopher William Beale
George Anthony Georgiou
Mark Andrew Robins
Benjamin Andrew Shnookal
Philip David Corbett
Michael Grant Roberts
Alistair Neill Murdoch
Nicholas Pane
Nicholas David Hopkins
Carolyn Hayley Sparke
Kevin Joseph Aloysius Lyons
Edvard William Alstergren
Andrew David Clements
Adrian John Finanzio
Bernard Francis Quinn
Saul Conrad Holt

Congratulations to all of those Counsel in 2012 that have been appointed Senior Counsel!

Wednesday, October 31, 2012

Civil Procedure Amendment Act 2012 receives royal assent and commences 1 May 2013

I attended the Commercial Bar Association annual cocktail party in the Supreme Court of Victoria library on 30 October 2012, and during his speech the Attorney-General Robert Clark noted that the Civil Procedure Amendment Act 2012 received Royal Assent that morning.

I previously wrote about the structure of the Civil Procedure Amendment Bill 2012 in my article Civil Procedure Amendment Bill 2012 - costs disclosure and expert evidence. The structure of the Act has not appeared to have changed since it was introduced as a Bill.

By way of summary, the Act:
  • empowers the Court to make orders about costs disclosure;
  • empowers the Court to make orders about the costs of proceedings;
  • empowers the Court to make orders managing expert witnesses; and
  • removes duplicative certification requirements for frequent litigants. 
The Civil Procedure Amendment Act 2012 commences as an amendment to the Civil Procedure Act 2010 on 1 May 2013.

The full authorised text from the Victorian Parliament is here.

On another note, at the cocktail party the Commercial Bar Association launched its new website: http://www.commbar.com.au

Tuesday, October 30, 2012

Prevention in 2012: Spiers Earthwords PL v Landtec Projects Corporation PL (No. 2) [2012] WASCA 53

In construction law the 'prevention' or 'Peak' principle was considered to have taken a turn for the worse after the two decisions of Turner Corporation Ltd v Co-ordinated Industries Pty Ltd (1995) 11 BCL 202 and Turner Corporation Ltd (receiver & manager appointed) v Austotel Pty Ltd (1997) 13 BCL 378. In the Turner cases, the New South Wales Supreme Court held (by way of summary) that a contractor is not able to claim that the principal prevented the contractor from reaching completion if the contractor failed to exercise its rights under the contract to claim an extension of time for such conduct.

Spiers Earthwords PL v Landtec Projects Corporation PL (No. 2) [2012] WASCA 53 (Spiers v Landtec) revisited the prevention principle in the context of the AS 2124-1986 standard contract (which is similar to the often used AS2124-1992 contract). The contractor claimed that it was prevented from reaching practical completion in respect of a contract for road works which had a 10 week completion period, and that the principal could not impose liquidated damages for the delay beyond the date for practical completion. The contractor claimed that the principal failed to supply sufficient or suitable material, that rectification was performed with unsuitable material, that additional works were undertaken at the principal's requests, that the principal made design changes and that there was inclement weather and also latent conditions.

The principal responded by saying that the contractor had not given notice requesting an extension of time (relying on the principle from the Turner cases). The contractor responded to this by saying that the principal requested additional work and the principal and superintendent had not responded to the contractor's requests for extensions of time, and was therefore estopped from relying on the contractor's failure to issue a notice under the contractual extension of time provisions.

The trial judge found that the principal was estopped from relying on the notice requirements of clause 35.5 in relation to 42 days, being a combination of additional work and rain delay, and that the date of the contract should be extended by 42 days. The contractor appealed this (although the finding was in the contractor's favour) as the contractor's position was that it didn't seek an extension of time, but instead sought that time be 'at large' (i.e. that completion occur within a reasonable time) by reason of the preventative conduct of the principal. The New South Wales Court of appeal upheld the trial judge's decision.

The contract in question (AS2124-1986) had a clause which expressed that principal or superintendent caused delays do not cause time to be set 'at large', in clause 35.5:
A delay by the Principal or the failure of the Superintendent to grant a reasonable extension of time or to grant an extension of time within 28 days shall not cause the Date for Practical Completion to be set at large but nothing in this paragraph shall prejudice any right of the Contractor to damages.
McLure P said that the Court was bound to follow Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211, which upheld the Turner cases. Peninsula Balmain approved the Turner cases, and also is authority for the proposition that the power of the superintendent to extend time in the absence of the required contractual notice from the contractor was to be exercised in the interests of both the principal and the contractor, and the superintendent is obliged to act honestly and impartially in considering whether to do so. The result in Peninsula Balmain was that the referee appointed by a court extended the date for practical completion as it considered that the superintendent (which didn't extend the time) ought to have done so.

In obiter, McLure P cast doubt on the proposition that anyone other than the superintendent can grant an extension of time (at [57]). That is, in Peninsula Balmain the referee exercised the power of the superintendent to extend time, but McLure P didn't consider that this was a power that could have been exercised by anyone other than the superintendent.

In Spiers v Landtec the contractor argued, along the lines set out in Peninsula Balmain, that (at [58]):
  1. the respondent had breached its duty to ensure the superintendent acted honestly and fairly as a result of the superintendent's breach of his duty to consider and, if appropriate, grant the appellant's requests for an extension of time regardless of the absence of any relevant notice; and
  2. in the alternative, by reason of waiver and/or estoppel of the requirement for notice, the superintendent was in breach of his obligation to consider and, if appropriate, grant an extension of time.
McLure P noted that the contractor's propositions ignored the paragraph in clause 35.5 set out above and that its purpose was 'to prevent the prevention principle having the effect of setting time at large' (at [61] and [62]):
61 Whether and to what extent cl 35.5 is intended to exclude the application of the prevention principle is a matter of contractual construction. The objectively determined purpose of cl 35.5 is at least twofold. The first is to provide contractual machinery to prevent the time for practical completion being set at large as a result of the application of the prevention principle. The second is to place on the principal the risk of delay caused loss not attributable to any contractual party. However, it would appear its purpose is not to exclude the prevention principle itself insofar as it applies to delay caused by the principal's breach of the building contract. In the absence of an extension of time under cl 35.5, the contractor would be entitled to damages against the principal for its breach of contract, including any damages (liquidated or otherwise) it suffered as a result of principal-caused delays in practical completion. Whether or not that could be relied on as a defence (such as equitable set-off) does not have to be decided. In the result, cl 35.5 brings the prevention principle back into line with the general contractual principles relating to the implied duty to cooperate. Accordingly, it is unnecessary to determine whether contractual parties are free to exclude the implied duty to cooperate, which is a term implied by law. 
62 The same analysis would apply to a (derivative) breach by the principal arising from a superintendent's breach of the duty to consider the exercise of the power in cl 35.5. Moreover, it is arguable that the prevention principle is a relevant consideration in the exercise of the superintendent's discretion to extend time in relation to the 'non-breach' causes of delay specified in cl 35.5. If a court or another decision-maker concludes that the superintendent should have exercised the power and granted an extension of time, the principal will be prevented from claiming liquidated damages for the relevant (proven) delay. In summary, the relevant purpose of cl 35.5 is to prevent the prevention principle having the effect of setting time at large.
McLure P held that on her analysis the principal would not be entitled to liquidated damages for the period for which the appellant should have been given an extension of time under clause 35.5, and upheld the decision of the trial judge. Newnes JA agreed with McLure P on these grounds.

Spiers v Landtec is particularly important for two reasons (in the context of the 'prevention principle'):
  1. The Court has questioned whether anyone other than the superintendent can extend time. This requires an analysis of the relevant contract the subject of a dispute to ascertain the scope of the power to extend time, and to determine whether anyone else can exercise this power.
  2. The Court has noted that the prevention principle is alive and well, at least to the extent that a principal may be precluded from relying on a claim for liquidated damages for a particular period of time during which that principal has contributed to the delay.
One of the difficulties, however, with the analysis of McLure P is that it is unclear how the conclusion is reached that the principal is not entitled to liquidated damages for the 42 days. For instance, it is not characterised by McLure P as an entitlement of the contractor in estoppel, despite the trial judge finding that this is how it was to be characterised.

Thursday, October 18, 2012

The Edelsten judgment (Beach J): possibly the best opening of any judgment ever.

In the matter of Norman South Pty Ltd & Anor v da Silva [2012] VSC 477, Justice Beach heard a breach of confidence claim. 

I won't go into any detail of the case in this post, other to extract the opening paragraph which states: 'A little over 13 years ago, Brooking J commenced a judgment with the statement “Titus Oates was the greatest perjurer that ever lived”.[1] Self-evidently, his Honour was not the trial judge in the present proceeding.'

Possibly one of the best opening lines to a judgment I have read. 

Thursday, October 11, 2012

The Fortescue decision: insights from the Commercial Court seminar

As I indicated on my article yesterday, I went to the Commercial Court seminar on the Fortescue decision which was handed down by the High Court of Australia on 2 October 2012.

The insights provided were helpful and interesting.

Justice Robson of the Supreme Court of Victoria noted that the main between the majority decision and Justice Heydon's decision was whether the statement by Fortescue amounted to an opinion. The majority opined that it did not, and Heydon J opined that it did. Justice Robson observed that the majority decision is likely to be used to reject an opinion based approach to the question of whether a statement is misleading or deceptive conduct.

The majority's approach is highlighted at [33]:
33. As has already been noted, ASIC's argument in this Court hinged on the proposition that the impugned statements conveyed to their intended audience a view about the legal enforceability of the framework agreements. ASIC sought to describe what was conveyed as a matter of fact, submitting that "the words 'agreement' or 'binding agreement' convey that it is an agreement containing all of the essential elements that would constitute a contract under Australian law". While it is to be doubted that the proposition which ASIC identified is accurately, or at least sufficiently, described as a statement of "fact", it is ultimately unprofitable to attempt to classify the statement according to some taxonomy, no matter whether that taxonomy adopts as its relevant classes fact and opinion, fact and law, or some mixture of these classes. It is necessary instead to examine more closely and identify more precisely what it is that the impugned statements conveyed to their audience.
Mark Moshinsky, SC, noted the main difference between the decision of the Full Court of the Federal Court of Australia (FCFCA) and the High Court was that the FCFCA looked at the correctness of the statement as a matter of legal enforceability whereas the High Court looked at what the parties did and intended to do. This is highlighted at [37] and [38]:
37. Would they, as the Full Court assumed, ask a lawyer's question and look not only to what the parties had said and done but also to what could or would happen in a court if the parties to the agreement fell out at some future time? Or would they take what was said as a statement of what the parties to the agreements understood that they had done and intended would happen in the future? The latter understanding is to be preferred. 
38. The Full Court's conclusion hinged on the use of the word "contract" or "agreement" in each of the impugned statements. The Full Court assumed that, by using one or other of those terms, the impugned statements conveyed to their intended audience a message about the legal quality (as determined by reference to Australian law) of the contract or agreement referred to in the relevant communication. And the relevant legal quality was identified as future enforceability in the event of a dispute between the parties. That is, the Full Court assumed that the words "contract" and "agreement" necessarily conveyed a message about legal enforceability in an Australian court. But that is too broad a proposition. First, it is necessary to examine the whole of the impugned statements to see the context in which reference was made to the making of a contract or agreement. Second, it is necessary to undertake that task without assuming that what is said must be put either into a box marked "fact" (identified according to whether an Australian court would enforce the agreement) or into a box marked "opinion" (identified according to whether the speaker thoughtthat an Australian court could or would enforce the agreement).
Senior counsel noted the implications of the decision were:
  • the reduced relevance of a distinction between what is a statement of fact and a statement of opinion;
  • in Justice Heydon's reasons, what principles are applied when there is a statement of opinion; and
  • the question of who is the intended audience.
Michael Kingston, the Chief Legal Officer of ASIC, noted that the impugned statements caused an enormous fluctuation in the Fortescue share price and induced a substantial number of share sales, bringing home the enormous effect of the statements on the market.

Mr Kingston questioned whether the standards for market disclosure were now lower than expected. Given the test for disclosure is [by way of broad summary only] what a reasonable person would have expected to have communicated to him or her, he questioned if now the market was required to 'read between the lines' when a disclosure is made, for instance, when a company enters into a 'binding contract' with a Chinese company as Fortescue did.

The Commercial Court seminar series has come to an end for 2012. Many thanks to Justice Davies for her efforts in organising and pulling together such a fantastic cast of speakers for the series.

Wednesday, October 10, 2012

The Fortescue decision: analysis and the Commercial Court seminar

I'm attending a seminar tonight held by the Commercial Court of the Supreme Court of Victoria on the Fortescue decision by the High Court of Australia: Forrest v Australian Securities and Investments Commission [2012] HCA 39. Here's a flyer for the seminar.

By way of summary Fortescue Metals Group Pty Ltd (Fortescue) signed, between 6 August 2004 and 20 October 2004, 3 4 page agreements with 3 Chinese state owned companies. It sent a letter to the ASX, together with a media release, in which Fortescue said that it had entered into a 'binding contract' with one of the companies. There were further statements made by Fortescue as and when it entered into the agreements with the other Chinese companies during that time.

The nub of ASIC's case was that the contracts weren't binding as Fortescue could not oblige the companies to abide by them, and for that reason, Fortescue engaged in misleading or deceptive conduct in relation to a financial product (being shares) in breach of s1041H Corporations Act; it breached the continuous disclosure requirements under s674 Corporations Act; and Mr Forrest had not exercised his powers or discharged his duties as a director of Fortescue with the degree of care and diligence required by s180 Corporations Act.

At first instance the matter went before Gimour J of the Federal Court of Australia who dismissed the case. The Full Court of the Federal Court allowed an appeal by ASIC, and Fortescue and Mr Forrest appealed to the High Court of Australia.

The Fortescue decision isn't particularly revolutionary as the High Court's attention is focused on what the intended audience would make of the representation that Fortescue had entered into binding contracts with Chinese state-owned companies.

The majority (French CJ, Gummow J, Hayne J and Kiefel J) identified the audience (at [36]):
36 There are at least two difficulties in the Full Court's analysis. Both stem, ultimately, from the need to identify the intended audience for the impugned statements and the message or messages conveyed to that audience. The intended audience can be sufficiently identified as investors (both present and possible future investors) and, perhaps, as some wider section of the commercial or business community. It is not necessary to identify the audience more precisely. When that audience was told that Fortescue had made binding contracts with identified Chinese state‑owned entities, what would they have understood?
The majority then went on to note that no evidence had been led by ASIC which would demonstrate that the audience would understand 'binding contracts' to mean contracts which are enforceable in a court (at [39]):
39. There was no evidence led at trial to show that investors or other members of the business or commercial community (whether in Australia or elsewhere) would have understood the references in the impugned statements to a "binding contract" as conveying not only that the parties had agreed upon what they said was a bargain intended to be binding, but also that a court (whether in Australia or elsewhere) would grant relief of some kind or another to one of the parties if, in the future, the opposite party would not carry out its part of the bargain.
The majority then went on to identify a critical problem, which was ASIC's case that the representation conveyed to the audience a larger message that the agreements were not open to challenge in an Australian Court (at [43]):
43 Once it is accepted, as it must be, that the parties genuinely intended to make a legally binding agreement, the breadth of ASIC's submission (and the Full Court's conclusion) becomes apparent. For the submission was that, although the impugned statements accurately recorded that the parties to each framework agreement had made an agreement which said that the bargain was, and was intended by the parties to be, legally binding, the impugned statements were misleading or deceptive or likely to mislead or deceive because they also conveyed to their intended audience a larger message. This was that the agreements the parties had made were not open to legal challenge in an Australian court. That broader proposition should not be accepted. The impugned statements conveyed to their intended audience what the parties to the framework agreements had done and said they had done. No further message was shown to have been conveyed to an "ordinary or reasonable" member of that audience.
The critical question about the audience was identified by the majority at [48]:

48. It is, however, necessary to bear firmly in mind that the impugned statements were made to the business and commercial community.  What would that audience make of the statement that Fortescue had made a binding contract with an entity owned and controlled by the People's Republic of China? 
This was answered by the majority at [50]:
50. Instead, the central tenet of ASIC's case was that the impugned statements conveyed a message to their intended audience (a) that, in the words of ASIC's statement of claim, it was "practicable to force" the counter‑parties to perform their part of the bargain and (b) that whether it was "practicable to force" performance was to be determined according to the same principles as would be applied to an agreement for the sale of a suburban block of land or the construction of a house in suburban Australia. ASIC established neither of those propositions. The impugned statements conveyed to their intended audience what the parties to the framework agreements said they had done — make agreements that they said were binding — and no more. ASIC did not demonstrate that members of the intended audience for the impugned statements would have taken what was said as directed in any way to what the parties to the agreements could do if the parties were later to disagree about performance. ASIC did not demonstrate that the impugned statements conveyed to that audience that such a disagreement could and would be determined by Australian law. And given that the impugned statements did accurately convey what the parties to the framework agreements had said in those agreements, it would be extreme or fanciful for the audience to understand the impugned statements as directing their attention to any question of enforcement by an Australian court if the parties later disagreed. Such an extreme or fanciful understanding should not be attributed to the ordinary or reasonable member of the audience receiving the impugned statements.
The conclusion by the majority was that the letter which Fortescue sent to the ASX accurately recorded what the agreement provided, and that that letter did not convey to its intended audience any message about whether an Australian Court would enforce that agreement. For that reason, the appeal was allowed by the majority across the board (at [58] to [60], [65] and [67]):
58. The letter which Fortescue sent to the ASX about having made the framework agreement with CREC was not misleading or deceptive and was not likely to mislead or deceive. That letter accurately recorded what the framework agreement provided. The letter did not convey to its intended audience any message about whether an Australian court would conclude that the agreement could be enforced. It conveyed to its intended audience that the framework agreement between Fortescue and CREC was what those parties had described (and a commercial audience would describe) as a "binding contract".

59.  Having regard to the way in which ASIC presented its argument in this Court, it is not necessary to consider separately the other impugned statements to which ASIC referred in its statement of claim. It is also unnecessary to give separate consideration to the "likely to mislead or deceive" limb of s 1041H. In the Full Court, Emmett J expressly based his reasons on this ground. His Honour concluded that the statements "were, at least, likely to mislead or deceive an ordinary and reasonable member of the investing public who read the [impugned statements]". But the inquiry into how an ordinary or reasonable member of the intended audience would receive a message is of its nature hypothetical. That inquiry is therefore apt to answer both whether conduct is misleading or deceptive and whether it is likely to mislead or deceive. Separate consideration of this limb of s 1041H is therefore not necessary once it is decided that an ordinary or reasonable member of the audience would not have understood the impugned statements to have conveyed anything other than what the parties did and intended, and that the statement made about those matters was neither misleading nor deceptive.

60.  ASIC did not establish that Fortescue engaged in misleading or deceptive conduct contrary to s 1041H of the Corporations Act. 
65.  For the reasons already given, the premise for ASIC's alternative argument about the application of s 674 was not established. The impugned statements did not express any relevant opinion. The impugned statements accurately conveyed to their intended audience what the agreements provided. That is reason enough to reject ASIC's alternative argument. Fortescue's statements having described accurately what the framework agreements provided, it is not to be supposed that s 674 nonetheless required Fortescue to publish the very text of those agreements. ASIC should have special leave to cross‑appeal but its cross‑appeal should be dismissed.
70.  ASIC's allegations that Mr Forrest breached the duties imposed by s 180(1) of the Corporations Act on directors and officers depended upon it demonstrating that Fortescue had contravened s 1041H or s 674. Having failed to do that, ASIC's claim of contravention of s 180(1) also fails.
Heydon J, in separate reasons, allowed the appeal, the summary of which is set out at [85]:
85. First, leaving aside issues relating to what was "contractually binding", the agreement was an agreement calculated to ensure that CREC built and financed a railway by compelling the parties to enter further negotiations about the further detailed agreements necessary to make certain that the railway was built within the framework – what cl 7 called the "intent" – of the agreement. Secondly, even if the agreement was not a "binding contract" to build the railway, it was a "binding contract" to engage in the necessary further negotiations and enter the necessary further agreements. Thirdly, so far as Fortescue had represented that there was a "binding contract" to build the railway, the statement was one of opinion, and only fell within s 1041H if ASIC established that Fortescue did not hold that opinion, or, if it did, that it had no reasonable basis for stating it. ASIC did not establish either proposition.
The more interesting aspect of the Fortescue decision was the heavy criticism of ASIC by all members of the High Court.

The majority took ASIC to task in the way it appeared to conflate a pleading on misleading or deceptive conduct with a pleading of fraud, and when this was explained by ASIC, took ASIC to task even further (at [24] and [25]):
24. ASIC sought to explain and justify the inclusion in its statement of claim of a plea that Fortescue had no genuine or reasonable basis for making the statements as a plea that anticipated Fortescue alleging that the impugned statements were expressions of opinion not fact. But it was neither necessary nor appropriate for ASIC to attempt to use its statement of claim to meet an answer that had not been made.

25. This is no pleader's quibble. It is a point that reflects fundamental requirements for the fair trial of allegations of contravention of law. It is for the party making those allegations (in this case ASIC) to identify the case which it seeks to make and to do that clearly and distinctly. The statement of claim in these matters did not do that.
Further, Heydon J at [89] agreed with D Jackson QC's submission that ASIC's pleaded characterisation of the agreement was 'absolute nonsense', describing it as 'false':

89 The above reasoning renders false the allegations in par 28(a)-(c) that the agreement "did not state that CREC would … build and finance the railway", or "construct it on a 'Build and Transfer' basis", or "complete any works". It also renders false the allegations in par 20(a) and (b) that the agreement "did not by its terms oblige CREC" either to "build or transfer a railway facility" or "to finance the construction of a railway facility". Mr D F Jackson QC submitted that leaving aside the question of contractual effect, "with respect, the contention that that is not the effect of the agreement is absolute nonsense." This submission was entirely correct in content, style and tone.
I'm interested in the insights which will come from the seminar, particularly since it is being presented by Michael Kingston, the Chief Legal Officer of ASIC and Mark Moshinsky SC, who appeared as one of the senior counsel for ASIC.


Monday, October 8, 2012

Litigation funding: International Litigation Partners Pte Ltd v Chameleon Mining NL [2012] HCA 45

The matter of International Litigation Partners Pte Ltd v Chameleon Mining NL (Receivers and Managers Appointed) [2012] HCA 45 was an appeal to the High Court of Australia from the Supreme Court of New South Wales.

International Litigation Partners Pte Ltd (ILP) entered into a litigation funding deed (the Deed) with Chameleon Mining NL (Chameleon) to fund litigation by Chameleon against Murchison Metals Ltd and others, claiming compensation for breach of statutory and fiduciary duties. Judgment was reserved in the Federal Court proceeding, and there was a restructure of Chameleon which triggered an 'Early Termination Fee' in the Deed. The fee was substantial, and was defined to mean 'an amount equal to "the Legal Costs (including Security for Costs)" expended by ILP up to the date of termination under cl 4.1 and a further amount being the higher of $9 million or the value of 20 per cent of the share capital of Chameleon at the "strike price" of its shares by the acquirer of the Change in Control' (at [10]).

In response to a claim by ILP for the fee, Chameleon gave a notice of rescission of the Deed under s925A Corporations Act, claiming that ILP ought to have had an Australian financial services license when entering into the Deed with Chameleon. While carrying on the business of litigation funding, ILP was not the holder of an Australian financial services license under Part 7.6 of the Corporations Act, and Chameleon argued that ILP should have been so licensed.

The majority (French CJ, Gummow, Crennan and Bell JJ) describe the operation of Part 7.6 of the Corporations Act as follows:
7. Part 7.6 of Ch 7 of the Act (ss 910A-926B) establishes a scheme for the licensing of providers of "financial services". Section 925A is of critical importance. It applies (by dint of s 924A) to an agreement with a client entered into in the course of a "financial services business" by a non-licensee who does not hold a licence and is not exempt from the requirement to do so, where the agreement constitutes or relates to the provision of a financial service by the non-licensee. Section 925A empowers the client to give to the non-licensee a written notice stating that the client wishes to rescind the agreement. This has the effect given by s 925E that the non-licensee is not entitled to enforce the agreement or to rely on it by way of defence or otherwise as against the client.
ILP argued that the provision of litigation funding to Chameleon was a 'credit facility' within the meaning of s765A(1)(h)(i) of the Corporations Act, which was exempt from the licensing requirement under Chapter 7 of the Corporations Act.

The Majority considered the Revised Explanatory Memorandum to the Financial Services Reform Act 2001 which stated that credit facilities were not covered by the definition of 'financial product' and to the extent they were consumer credit, they would be regulated by the State based Uniform Consumer Credit Code (which was displaced by the National Consumer Credit Protection Act 2009) (at [23]).

The majority considered the definition of a credit facility under the Corporations Regulations (at [26]):
26. Subject to exclusions which do not apply, the provision of "credit ... for any period", with or without prior agreement between the credit provider and the debtor and whether or not both credit and debit facilities are available, is a "credit facility" (reg 7.1.06(1)(a)). The term "credit" is defined in reg 7.1.06(3)(a) as meaning a contract, arrangement or understanding under which payment of a debt to the credit provider "is deferred", and as including "any form of financial accommodation" (reg 7.1.06(3)(b)(i)). The use in this way of the concept "means and includes" is to avoid any doubt that what is identified by the inclusion falls within the scope of the designated meaning of "credit"[11]. The result is that a contract, arrangement or understanding that is any form of financial accommodation is "credit", and its provision "for any period" will be a "credit facility".
The majority noted that the principal obligation of ILP in the Deed was to pay 'Legal Costs' within 28 days of receipt of written notification requiring payment, and upon resolution of the proceedings in favour of Chameleon, whether by settlement of judgment, ILP would be entitled to repayment of the 'Legal Costs' paid by it together with a 'Funding Fee'. The majority held that this was a form of financial accommodation provided by ILP to Chameleon, notwithstanding that ILP was to pay the 'Legal Costs' incurred by Chameleon, rather than advancing to it the moneys to enable it to do so itself (at [29] to [32]):
29. The principal obligation undertaken by ILP in the Funding Deed was its agreement in cl 2.1 to pay the "Legal Costs" within 28 days of receipt of written notification requiring payment. "Legal Costs" were defined as all costs associated with procuring the files of Chameleon's previous solicitor in the Federal Court proceedings, and all future agreed legal costs and disbursements incurred by Chameleon and ILP in relation to those proceedings or any appeal (cl 1). Upon resolution of the proceedings in favour of Chameleon, whether by settlement or judgment, ILP would be entitled (cl 3.1(a)) to "Repayment" of the Legal Costs it had paid in accordance with cl 2.1; ILP also would be entitled to payment of the "Funding Fee" (cl 3.1(b)). This was an amount being the higher of three times the costs incurred by ILP under cl 2.1 and the "Percentage Payment" out of the "Resolution Sum", being the gross amount received upon settlement or judgment in the proceedings. The "Resolution Sum" was to be held by Chameleon's solicitors on trust for ILP, as to so much thereof as was due to ILP under the Funding Deed (cl 3.3). 
30. Hodgson JA was of the view that what the Funding Deed provided to Chameleon was a form of financial accommodation[13]. This was so, in our opinion, notwithstanding that ILP was to pay the Legal Costs incurred by Chameleon rather than advancing to it the moneys to enable it to do so. 
31. In its submissions, Cape Lambert emphasised that reg 7.1.06(1)(a)(i) defined "credit facility" for s 765A(1)(h)(i) of the Act as "the provision of credit ... for any period". This was said to require identification in the Funding Deed of a period of time when there was money owing by Chameleon but not payable. This reflected too narrow a view of what might amount to the provision for a period of "credit" by a form of financial accommodation. This is true also of the submission made by Chameleon that "financial accommodation" postulated an obligation by Chameleon to pay money which was deferred, the deferral representing the accommodation. A bank overdraft may be subject to a term that it be repayable on demand by the bank, but the facility is one of accommodation for that period which elapses before the demand is made. 
32. Clause 2.1 of the Funding Deed contained a present promise by ILP to pay the Legal Costs within 28 days of receipt of written notification. The temporal limitation upon the performance of that promise was that the notification relate to costs in relation to the Federal Court proceedings or any appeal from a judgment or order therein. For its part, Chameleon undertook to make the payments identified in cl 3.1 if the Federal Court proceedings yielded a receipt whether by way of settlement or judgment.
Heydon J agreed with the majority in separate reasons.

The ILP v Chameleon decision is important for the litigation funding industry as it is authority for the proposition that similar funding agreements are 'credit facilities' which are exempt from the licensing requirements under Chapter 7 of the Corporations Act.

Monday, September 3, 2012

Disclaimer of a lease by a landlord update: Re Willmott Forests [2012] VSCA 202.

I wrote a post on disclaimer of a lease by a landlord in 'Disclaimer of a lease by a landlord: Willmott Forests Ltd [2012] VSC 29'. That matter was a decision by Davies J in which Her Honour held that a landlord could not disclaim a lease, under s568 Corporations Act, for the following reasons (at [11]):
a disclaimer of the lease by the liquidator of the landlord would only terminate the rights, interests, liabilities and property of the landlord but it would not bring the lease to an end for all purposes. Specifically, it would not bring the tenant’s proprietary interest in the land to an end. The tenant’s proprietary rights in the land will continue to subsist, even though the effect of disclaimer is that the landlord’s interests and liabilities under the lease have been terminated. Thus the effect of disclaimer is different where the lease is disclaimed by the liquidator of the landlord.
That decision was appealed, and the Court of Appeal (Warren CJ, Redlich JA and Sifris AJA) upheld the appeal in Re Willmott Forests [2012] VSCA 202. I haven't linked the AustLII decision to this page as the decision is not available yet. However the decision is available on the ABL website section devoted to the Willmott Forests liquidation litigation (http://www.abl.com.au/willmott/willmott.htm).

Warren CJ and Sifris AJA summarised the critical question as follows (at [1]): 'The critical question in this appeal is whether a leasehold interest in land is extinguished by the disclaimer of the lease agreement by the liquidator of the lessor, pursuant to s 568(1) of the Corporations Act 2001 (Cth) ('the Act').'

The Court of Appeal considered that if the interest of a lessee under a disclaimed contract terminated, then the leasehold estate must also go.

Warren CJ and Sifris AJA construed s568D(1) Corporations Act widely and considered that it included the obligation to provide possession and quiet enjoyment (at [37]):
37. The context of the word 'liability' in s 568D(l) suggests that it should be given the widest possible meaning and include the obligation to provide possession and quiet enjoyment. The section is specifically designed to enable a liquidator 'to cease performing obligations ... [and] to achieve a release of the company in liquidation from its obligations'. If WFL is to be relieved of its obligation to provide quiet enjoyment, clearly and in context a liability, the interest of the lessee so far as tenure is concerned is directly related to and underpins such liability. The tenure must go. It is necessary to affect the Growers rights (tenure) in order to release WFL from its liability (possession and quiet enjoyment). The cases where rights have been preserved usually involve claims against third parties unrelated to any liability of the company in liquidation.
Warren CJ and Sifris AJA relied on the decision of Deane J in Progressive Mailing House Proprietary Limited v Tabali Proprietary Limited (1985) 157 CLR 17 (at [42] of Willmott):
[T]he leasehold estate cannot be divorced from its origins and basis in the law of contract (c.f. per Aitkin L.J. in Matthew v Curling): the lease should be seen as 'resting on covenant' (or contractual promise) and it is 'the contract ... and not the state ... which is the determining factor': see per Isaacs J., Frith v O'Halloran quoting from Hallen v Spaeth.
...
[O]nce it is accepted that the principles of the law of contract  governing termination for fundamental breach are, as a matter of theory, applicable to leases generally, there is no difficulty in applying them in the present case in much the same fashion as an ordinary executory contract: '[i]f the contract is avoided or dissolved ... the estate falls with it': per Lord Wright, Cricklewood Property and Investment Trust Ltd v Leighton's Investment Trust Ltd.
Warren CJ and Sifris AJA held that because the leasehold interest is governed by the law of contract, the consequences of disclaimer of a contract of lease were no different to those for termination of a lease by way of acceptance of a repudiation (at [47]):
47. Although the event bringing about the termination of the contract of lease (and as a consequence, any leasehold interest) was a repudiation accepted by the non-defaulting party, it is the consequences of such termination, (namely termination of the leasehold interest) however brought about, that are relevant. There is no reason in principle or policy that should treat the consequences of disclaiming a contract of lease in a different way. In both cases, the lease agreement is at an end and what follows is a matter of law, namely termination of the leasehold interest that does not depend in any way on the reason for such termination. 
Warren CJ and Sifris AJA held that the leasehold interest could not survive the termination of the very document that created it and regulated the tenure of the Grower, and held that the policy of the Corporations Act, particularly the disclaimer provisions, supported the appellant's position (at [58]):
58. Accordingly, in our opinion, the grounds of appeal are made out. For the reasons given, any leasehold interest cannot survive the termination of the very contract that created it and regulated the tenure of the Grower. It is this tenure which creates, and is the basis of, the obligation or liability on the part of WFL to provide quiet enjoyment. Section 586D(1) allows the liquidator to terminate this obligation or liability despite its intrusion into the property rights of an innocent party. The evident policy is to permit the loss of these rights in order to enable the company in liquidation to be free of obligations so that it can be wound up without delay for the benefit of its creditors. To compensate, the rights of the affected parties are transmuted into various statutory rights and claims.
Redlich JA also held that s568D ought to be construed widely (at [82]):
82. Save where the terms of the lease provide otherwise, the landlord will ordinarily be obliged to meet various expenses arising from ownership of the freehold to ensure the tenant's undisturbed possession of the land. But 'liability' in the context of s 568D is not to be confined to a financial obligation or immediate financial detriment. There is nothing in s 568D or Div 7 A to suggest that the term liability is not so wide as to include 'a legal obligation or duty.' The term 'liability' has a broad meaning which covers executory obligations in relation to the quiet possession, use and enjoyment of the land into the future. To release the appellants from these obligations it is necessary that the respondents' estates or interests in the leased lands be extinguished at the same time as the contracts. 

Wednesday, July 25, 2012

Amendment vs removal of caveats: Ren v Shi [2012] VSC 271

I was recently involved in the matter of Ren v Shi [2012] VSC 271 which was a hearing before Justice McMillan in the Supreme Court of Victoria. The plaintiff was seeking to remove a caveat from a property, and the defendant alleged that the caveat ought to remain on the title as, although defective, it was said to be capable of amendment.

The defect in the caveat was largely in the section 'estate or interest claimed'. The caveat claimed an 'estate in fee simple' (i.e. stating that the caveator was the owner of the land), whereas it appeared that the interest that the caveator had could only be, at its highest, an equitable charge (at [34] to [37]). Also, the document (written in Chinese) said to give rise to the interest was translated as follows (at [33]):
The plaintiff’s translation reads “[Mr] Xiao agrees to use his family assets to guarantee the repayment of the debt owed to [Mr]Shi”. In contrast, the defendant’s translation reads “[Mr] Xiao agrees to use his family assets as security for the repayment of the debt owed to [Mr] Shi”.
Power to amend a defective caveat

s90(3) of the Transfer of Land Act 1958 (Vic) (the TLA) provides:
(3) Any person who is adversely affected by any such caveat may bring proceedings in a court against the caveator for the removal of the caveat and the court may make such order as the court thinks fit. [emphasis mine]
s90(3) TLA has been construed widely, giving the Court a discretion not only to remove a caveat, but also to amend the caveat to cure certain defects on the face of the caveat. There had been ongoing debate about whether or not the power to amend a caveat extends to amending the 'estate or interest claimed'.

In Ren v Shi, the McMillan J noted the factors that a Court must consider when faced with a defective caveat and an application to amend, including (at [21]):
(a) Whether the amendment is to the estate or interest claimed and not just the grounds of claim.
(b) The circumstances in which the error was made, including whether the caveator was represented by lawyers at the time.
(c) “The Court should not readily act in a way which might encourage the belief that the caveats can be imprecisely formulated and then ’fixed up later’.”
(d) The overall merits of the claim.
These factors developed from the decision of Macaulay J in Percy & Michele Pty Ltd v Gangemi [2010] VSC 530 (Gangemi) and were fleshed out by Dixon J in Martorella v Innovision Developments Pty Ltd [2011] VSC 282 (Martorella). Much earlier, in Midwarren Estates Pty Ltd v Retek & Stivic [1975] VR 575, Menhennit J held that the 'estate or interest claimed' could not be amended. However, Macaulay J in Gangemi and Dixon J in Martorella held that the 'estate or interest claimed' section in a caveat could be amended, but in considering the four factors set out above, special circumstances had to exist for such an amendment to be allowed (see Martorella at [65]).

The reasons for the limitation are discussed by Dixon J in Martorella in detail between [51] and [66]. A succinct summary is set out by Dixon J in Martorella at [55]:
A person proposing to deal with the land is entitled to assume that the claim expressed is the only one made, for the express mention of one ground is to the exclusion of the other. If a caveator enjoyed more, or different, rights in land than claimed in the caveat, it is proper and appropriate to lodge another, or a different, caveat notifying such interests.
For instance, it would be unfair for a registered proprietor to issue proceedings against a caveator, knowing that the caveator doesn't have the particular interest claimed, only to have the Court cure the defective caveat to the benefit of the caveator and to the detriment of the registered proprietor.

Removal of a caveat

McMillan J went on to discuss the considerations for the exercise of the Court's discretion to order the removal of a caveat. The basis for the removal of a caveat is the same as for an interlocutory injunction, as noted by Warren CJ in Piroshenko v Grojsman (2010) 27 VR 489 (Piroshenkoat [7] (also in Ren v Shi at [30]):
Caveats under the Torrens system are treated by the courts as analogous to applications for interlocutory injunctive relief. In so far as their registration is an administrative act, it is when application is made for their removal that the onus falls on the caveator to satisfy the two-stage test used by the court when deciding whether to exercise its discretion to grant injunctive relief. ... This two-stage approach requires the caveator to establish that there is a serious question to be tried that they have the estate or interest which they claim in the land in question, and having done so, to establish that the balance of convenience favours the maintenance of the caveat on the Register of Titles until trial.
Australian Broadcasting Corporation v O’Neill [2006] 227 CLR 57 clarified the proper test for a Court exercising its discretion to grant an interlocutory injunction. As a result, the trial division of the Supreme Court of Victoria recently reformulated the test for the removal of caveats, particularly with respect to the first arm of the test, being whether there is a 'serious question to be tried'. The test is as follows (Piroshenko v Grojsman [2010] VSC 240 at [18] and Ren v Shi at [31]):

1. there is a probability on the evidence before the court that he or she will be found to have the asserted equitable rights or interest; and
2. that probability is sufficient to justify the practical effect which the caveat has on the ability of the registered proprietor to deal with the property in question in accordance with their normal proprietary rights.
If there is a 'serious question to be tried', then the Court goes on to consider the 'balance of convenience'. The 'balance of convenience' test has had a similar re-expression as a result of the Court of Appeal in Bradto Pty Ltd v State of Victoria [2006] VSCA 89 rejigging the 'balance of convenience' test for interlocutory injunctions. This has been expressed as 'the court should take whichever course appears to carry the lower risk of injustice if it should turn out to have been ‘wrong’ (see Bradto at [35] and Ren v Shi at [38]).

Ultimately, McMillan J held that the caveat ought not be amended ([25]), and even if it was amended, the Court would order its removal as there was no serious question to be tried (at [37]), nor would the balance of convenience favour the retention of the caveat (at [38]).

Ren v Shi is a good summary of the factors which influence the exercise of the Court's discretion under s90(3) TLA. It also discusses the circumstances in which a Court will award compensation for a caveat lodged without reasonable cause under s118 TLA, and when an award of indemnity costs ought to be made against a caveator, but these topics are beyond the scope of this post.

Tuesday, June 26, 2012

Civil Procedure Amendment Bill 2012 - costs disclosure and expert evidence

The Civil Procedure Amendment Bill 2012 was recently introduced into the Victorian Parliament by Attorney-General Robert Clark and is currently being considered by the lower house. The Civil Procedure Amendment Bill 2012 is an amendment to the Civil Procedure Act 2010.

The explanatory memorandum of the Civil Procedure Amendment Bill 2012 notes that it is being introduced to give additional powers and discretions for the Courts in relation to costs disclosure and expert evidence:
The Civil Procedure Amendment Bill 2012 amends the Civil Procedure Act 2010 to introduce specific powers and discretions for the courts in relation to costs and expert evidence, to amend and create greater flexibility in the overarching obligations and proper basis certification requirements and to make other technical amendments.

The Bill aims to reduce costs and delays for persons involved in civil litigation in Victoria, and improve the effectiveness of the civil justice system. The Bill builds on the foundation established by the Civil Procedure Act 2010 in seeking to give judges and magistrates a clear legislative mandate to proactively manage cases in a manner that will promote the just, efficient, timely and cost-effective resolution of the real issues in dispute in a civil proceeding.
Part 2 of the Civil Procedure Amendment Bill 2012 gives the Court power to require costs disclosure to a lawyer's own client, and expands the type of costs orders which are able to be made:
Disclosure of litigation costs by a lawyer to his or her client is critical for informed decision-making. The Bill gives the courts a discretionary power to order that a lawyer make costs disclosure to the lawyer's own client. The order may be made at any stage of the proceeding. This will allow the courts, in appropriate cases, to increase the parties' access to information in relation to actual and estimated costs and disbursements incurred prior to trial, thereby encouraging more informed decision-making and the settlement of appropriate cases. 
The Bill also clarifies and strengthens the courts' discretionary power to make other costs orders aside from the usual order that the losing party pay the winning party's costs. The Bill provides that the court may make any costs order that it considers appropriate to further the overarching purpose. Specific powers include ordering costs as a lump sum figure instead of taxed costs, ordering a party to pay a proportion of costs or fixing or capping recoverable costs in advance. Such orders avoid or narrow the scope of a taxation of costs. The objective is to increase the use of other costs orders in appropriate cases, thereby reducing the complexity, time and cost associated with taxation. Orders may be made in relation to any aspect of a proceeding, including, but not limited to, any interlocutory proceeding.
Part 3 of the Civil Procedure Amendment Bill 2012 gives the Court greater power to manage expert evidence, including requiring parties to seek directions if the party intends to adduce expert evidence at trial, ordering conferences and joint reports and limiting expert evidence in Court:

Expert evidence plays a critical role in civil litigation and is often essential to the just determination of an issue in dispute between the parties. However, expert evidence can also be a significant source of expense, complexity and delay in civil litigation. For example, the disproportionate use of expert witnesses has the potential to increase costs and delays for parties and reduce the effectiveness of the civil justice system as a whole. The inherent complexity and volume of expert evidence can also limit its usefulness to decision-makers.

The main objective of the expert evidence provisions is to reduce the costs and delays associated with expert evidence by providing clear legislative guidance and encouragement for the courts to actively manage and control expert evidence. The provisions also aim to improve the quality and integrity of expert evidence and enhance its usefulness to judges and magistrates.

Some of the expert evidence provisions consolidate existing powers of the courts, for example in the rules of court and practice directions. Although the existing powers of the court may be sufficient for the court to give directions and impose reasonable limits on any party in respect of expert evidence, clear statutory provisions will have greater impact in encouraging the courts to actively manage and control expert evidence. This will also resolve any argument about the limits of existing rule-making powers and will overcome any constraints on the exercise of powers that exist at common law.
Finally, the Civil Procedure Amendment Bill 2012 amends the certification requirements, including extending certification to any 'substantive document' that a party relies on (with some qualification).

The expert provisions appear to be detailed and, if the Civil Procedure Amendment Bill 2012 is passed and given Royal Assent, practitioners will need to quickly get up to speed with the detail in the bill. The proposed commencement date is 1 May 2012 or on proclamation.